Activity Constraint / Primary Constraint
|
- If ACT_TYPE =
ALAP or
L, then value is
As Late As Possible
- If TARGSTYPE =
None and TARGFTYPE =
None, then value is
None.
- If TARGSTYPE =
None and TARGFTYPE =
No Earlier Than or
NE, then value is
Finish On Or After.
- If TARGSTYPE =
None and TARGFTYPE =
Not Later Than or
NL, then value is
Finish On Or Before.
- If TARGSTYPE =
None and TARGFTYPE =
On Target or
ON, then value is
Must Finish On.
- If TARGSTYPE =
None and TARGFTYPE =
Fixed Target, then value is
Mandatory Finish.
- If TARGSTYPE =
Not Earlier Than or
NE, then value is
Start On Or After.
- If TARGSTYPE =
Not Later Than or
NL, then value is
Start On Or Before.
- If TARGSTYPE =
On Target or
ON, then value is
Must Start On.
- If TARGSTYPE =
Fixed Target or
FT, then value is
Mandatory Start.
|
Primary Constraint Date
|
- If Activity Constraint / Primary Constraint is
Start On Or After,
Start On Or Before,
Must Start On, or
Mandatory Start, then value is
TSDATE.
- If Activity Constraint / Primary Constraint is
Finish On Or After,
Finish On Or Before,
Must Finish On, or
Mandatory Finish, then value is
TFDATE.
|
Secondary Constraint
|
- If Activity Constraint / Primary Constraint is set to
Start On Or After,
Start On Or Before,
Must Start On, or
Mandatory Start, then value is:
- Finish On Or After if TARGFTYPE is
Not Earlier Than or
NE.
- Finish On Or Before if TARGFTYPE is
Not Later Than or
NL.
- Must Finish On if TARGFTYPE is
On Target or
ON.
- Mandatory Finish if TARGFTYPE is
Fixed Target or
FX.
- If Activity Constraint / Primary Constraint is
Finish On Or After,
Finish On Or Before,
Must Finish On, or
Mandatory Finish, then value is
None.
|
Secondary Constraint Date
|
- If Secondary Constraint has a value, then field value is
TFDATE.
|
Activity Status
|
- If COMPSTAT is
Complete or
2, then value is
Complete.
- If COMSTAT is
In Progress or
1, then value is
In Progress.
|
Activity Type
|
- If ACT_TYPE is
Finish Milestone or
F, then value is
Finish Milestone.
- If ACT_TYPE is
Start Milestone or
S, then value is
Milestone.
- If ACT_TYPE is
Hammock or
H, then value is
Level of Effort.
- If ACT_TYPE is
Subproject,
External Subproject,
E, or
P, then value is
Summary.
- If none of the above, then value is
Normal.
|
Critical and Longest Path
|
- If CRITICAL is not
Not Critical and not
0, then the value is
True, otherwise the value is
False.
|
Duration Percent Complete
|
- Value is
Remaining Duration / Total Duration.
|
Earned Value Technique
|
- If EVT is
Level of Effort or
A, then value is
Level of Effort.
- If EVT is
Percent Complete or
C, then value is
Percent Complete.
- If EVT is
50-50 or
E, then value is
Fifty Fifty.
- If EVT is
0-100 or
F, then value is
Zero Hundred.
- If EVT is
User-Defined Percentage or
H, then value is
User Defined.
- If EVT is
Planning Package or
K, then value is
Planning Package.
- If EVT is
Resource % Complete or
L, then value is
Assignment Percentage Complete.
- If EVT is anything other than the above, then value is
Percent Complete.
|
Existence %
|
- If ACT_PROBABILITY is
blank, then value is
100, otherwise value is
ACT_PROBABILITY.
|
Finish Date
|
- If AFDATE exists, then use
AFDATE, otherwise use
EFDATE.
|
Start Date
|
- If ASDATE exists, then use
ASDATE, otherwise use
ESDATE.
|
Remaining Duration
|
- If PROGTYPE has a value of
R, then value is
PROGVALUE, otherwise value is
REM_DUR.
- If value of REM_DUR is less than 0, then value is reset to
0.
|
Is Level of Effort
|
- If ACT_TYPE is
Hammock or
H, then value is
TRUE, otherwise value is
False.
|
Remaining Duration Elapsed
|
- If PROGTYPE is
E, then value is
TRUE, otherwise value is
False.
|
Mean Duration or Most Likely Duration
|
- If REM_DUR is empty, then value is
0, otherwise value is
REM_DUR.
|
Maximum Lags
|
- Find the largest value of lag from the activity's list of successors.
|
Minimum Lags
|
- Find the smallest value of lag from the activity's list of successors.
|
Number of FS Predecessors
|
- Find the number of predecessors of the activity that have a link type of
Finish to Start.
|
Number of FS Successors
|
- Find the number of successors of the activity that have a link type of
Finish to Start.
|
Number of SS Predecessors
|
- Find the number of predecessors of the activity that have a link type of
Start to Start.
|
Number of SS Successors
|
- Find the number of successors of the activity that have a link type of
Start to Start.
|
Number of SF Predecessors
|
- Find the number of predecessors of the activity that have a link type of
Start to Finish.
|
Number of SF Successors
|
- Find the number of successors of the activity that have a link type of
Start to Finish.
|
Number of FF Predecessors
|
- Find the number of predecessors of the activity that have a link type of
Finish to Finish.
|
Number of FF Successors
|
- Find the number of successors of the activity that have a link type of
Finish to Finish.
|
Number of Lags
|
- Find the number of predecessors of the activity that have a positive value of
Lag.
|
Number of Leads
|
- Find the number of predecessors of the activity that have a negative value of
Lag.
|
Number of Predecessors
|
- Find the number of predecessors of the activity.
|
Number of Successors
|
- Find the number of successors of the activity.
|
Percent Complete
|
|
Project Time Now
|
- If STATDATE has a value, use
STATDATE otherwise use
STARTDATE.
|
Total Cost
|
- Actual Cost + Remaining Cost.
|
Total Duration
|
- Actual Duration + Remaining Duration.
|
Units Percent Complete
|
- Remaining Units / Total Units.
|
Percent Complete Type
|
- Value is always set to
Physical.
|
WBS
|
- If Activity Type is
Summary, then value is the WBS' generated GUID.
|